Update cef and obs-studio packages #16

Closed
opened 2026-09-01 22:02:25 +00:00 by dherrera · 3 comments
Owner

Both are out of date to latest upstream releases, and EPEL branches most likely will need some updates too.

Both are out of date to latest upstream releases, and EPEL branches most likely will need some updates too.
Author
Owner

Current progress on this task:

Was able to update cef to version 151.0.11^chromium151.0.7922.173 and it works on obs 32.2.2. Some notes on the progress:

  • Updated cef to the 7922 branch (XXX commit)
  • Cherrypicked 53 patches from the chromium package...
  • Current version of obs (32.1.1) crashes with the cef update
  • New version of obs (32.2.2) works fine with the cef update, will need to push both updates toguether.
  • Some of Fedora's downstream patches broke with the update. Fixing in progress...

TODO:

  • Create cef PR
  • Fix OBS patches
  • Create obs PR
  • Update package.
  • Check if EPEL versions can get update.
Current progress on this task: Was able to update cef to version 151.0.11^chromium151.0.7922.173 and it works on obs 32.2.2. Some notes on the progress: * Updated cef to the 7922 branch (XXX commit) * Cherrypicked 53 patches from the chromium package... * Current version of obs (32.1.1) crashes with the cef update * New version of obs (32.2.2) works fine with the cef update, will need to push both updates toguether. * Some of Fedora's downstream patches broke with the update. Fixing in progress... TODO: * Create cef PR * Fix OBS patches * Create obs PR * Update package. * Check if EPEL versions can get update.
Author
Owner
* cef PR created! https://src.fedoraproject.org/rpms/cef/pull-request/4 * obs-studio PR created! https://src.fedoraproject.org/rpms/obs-studio/pull-request/16 * Still need to fix patches 0101, 0102, 0103 and 1001.
dherrera changed title from Update cef and obs packages to Update cef and obs-studio packages 2026-09-02 23:54:07 +00:00
Author
Owner

updates to cef and obs-studio got merged 👍

updates to cef and obs-studio got merged 👍
Sign in to join this conversation.
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set.

Reference
epel/misc#16
No description provided.